6.2 Preparing for operation
6 Commissioning
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
6-4
6.2.3 Download modified project to the PNOZmulti safety system
Download modified project to the PNOZmulti safety system6-Verdrahtung_multi_Modul_Betr_geaend_Projekt_BA
As soon as an additional expansion module has been connected to the
system, the project must be amended using the PNOZmulti Configura-
tor. Proceed as described in the operating instructions for the base unit.
6.2.4 Connection example
Connection example6-_Dummy-Vorlage
NOTICE
For the commissioning and after every program change, you
must check whether the safety devices are functioning correctly.
CANopen
Master
CANopen
Slave 1
CANopen
Slave 2
CANopen
Slave 3
CANopen
Slave n
PNOZ mmc6p CANopen